A Roman Corner update from AJC Site Manager, Paul Whittaker

Share

Work is progressing at Roman Corner. AJC’s Site Manager, Paul Whittaker, has provided information on the current build stage and key milestone dates:
"Scaffold has now been lifted to gable height to allow gable ends to be lifted and topped out. Crendon have now installed all roof trusses and are now forming the valley gutter detail.

Our roofing contractor MC roofing, are progressing well with roof coverings Felt and Batten has been completed and the installation of Spanish tiles has started." 

Milestones 

  • First floor planks installation completed 9th June as per program
  • Second floor planks installation completed 21st July as per program 

Upcoming planned dates:

  • Roof completion fully in the dry (16th October).
  • 1st fix trades start on the ground floor (12th October)
  • Scaffold strike from 6th lift to 4th lift (19th October) 
  • Juliet balcony installation (26th October) 

Felt and Batten installation

Spanish Slate installation

Exterior progress

Exterior - site office

"AJC are passionate about building affordable homes, and as part of our commitment, we pledge our ‘500 in 5’ initiative in January 2023 to tackle the region’s critical shortage of genuinely affordable homes. Now halfway through our five-year target, we have completed 10 developments, with five more currently under construction. Roman Corner supports our pledge and mission to provide affordable housing across the Wessex region."

AJC are committed to not only making progress on the build but building a relationship with the local community. The Project Team completed a litter pick in Dorchester Gardens on Thursday 30th July, collecting 4 full bags of rubbish. They will continue to work on community projects throughout the project. 