Update from the Contractors, AJC

Share

Rapid progress continues to be made at Roman Corner. This month we have received a comprehensive update from the building contractor, AJC.

For the less technically minded:

  • a crash deck is a temporary safety platform to prevent falls and
  • a lift is the phase of brickwork. Each section of brick work and scaffold is classed as a “lift”.

Work is progressing at Roman Corner. AJC’s Site Manager, Paul Whittaker has provided information on current build stage and keep milestone dates.

Scaffold has now been lifted to 4th lift to allow the 2nd floor planks to be installed and 5th lift block and brickwork to be formed.

A&G brickwork will take approximately 10 days to form all block and face brickwork to the 5th lift, once we are at a point where block work has been taken up a level, we then install a crash deck to the internal rooms so we then can install 5th lift scaffold.

The crash deck will be installed on Friday 7th August.

5th lift scaffold installation date is the 11th August this will take 3 days to install.

Once we are at scaffold height, we can then take the block and face brick work up to allow us to install the steels which will take the roof trusses.

Ground floor.

Is set and ready to start internal trades.

Milestones

First floor planks installation completed 9th June. Second floor planks installation completed 21st July.

Up and coming planned dates.

  • Crash deck install Friday 7th August
  • 5th lift scaffold install date 11th August.
  • 6th lift brick and block work 18th August.
  • Structural steel work 25th August
  • Roof truss install 2nd September

AJC are passionate about building affordable homes and as part of our commitment we pledge our ‘500 in 5’ initiative in January 2023 to tackle the region’s critical shortage of genuinely affordable homes. Now halfway through our five-year target, we have completed 10 developments, with five more currently under construction.

Roman Corner supports our pledge and mission to provide affordable housing across the Wessex region.  

AJC are committed to not only making progress on the build but building our relationship with the local community.

Our Project Team completed a litter pick in Dorchester Gardens on Thursday 30th July where we collected 4 sacks full bags of rubbish. We will continue to work on community projects throughout the project.

Other News